Posted by Paul (184.32.180.214) on 09:20:34 02/05/13
In Reply to: 124 days 3 hours 55 minutes posted by Granite Head
86 days and the construction crews are moving toward completion. Slate is laid today. Fire wood delivered and in use. Carpet goes in Thursday. New beds arrive in 21 days. Kitchen floor is to be completed on Friday. Fencing is awaiting wind die down. Painting complete. Chair rail finished. Bird feeders in place. Many many birds present. Landscape begins again April 20 with detritus and stones to be placed. Fire control well in place.
Truly it is becomg Wa-co-ti Was-te, A good camp.